[59753] in Hotline Meeting
Bldg. 66 - Air Handler 1 Shutdown/Re-Install Chilled Water Coils
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 23 08:20:05 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231F2D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'kkgleasn@mit.edu'" <kkgleasn@MIT.Edu>,
"'patsys@mit.edu'"
<patsys@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'swetzel@mit.edu'" <swetzel@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 23 May 2002 08:20:00 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; kkgleasn@mit.edu; patsys@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - Air Handler 1 Shutdown/Re-Install Chilled Water
> Coils
>
>
The Facilities Department would like to re-install the chilled water coils
to Air Handler 1 for Bldg. 66 - Floors 1 through 5 North on Tuesday, 5/28
and Wednesday, 5/29. Would you please advise if this has approval or does
not.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 66 - Floors 1 through 5 North
> Date: 5/28/2002
> Day: Tuesday
> Time: (5/28) 7 AM - 7 PM & (5/29) 7 AM - 3 PM
> System: Air Handler 1
> Duration: 12 hours on 5/28 & 8 hours on 5/29
> Reason:
> Re-install chilled water coils to Air Handler 1.
>
> Effect:
> Loss of chilled water to Air Handler 1 (affects supply cooling and supply
> heating) during the shutdown period.
>
>