Bldg. 12 - Revised, Rescheduled Building Power Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 10 09:16:21 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231E74@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bkaynor@mit.edu'" <bkaynor@mit.edu>,
        "'caferrar@mit.edu'"
	 <caferrar@mit.edu>,
        Cust-Coach <cust-coach@mit.edu>,
        "'granvill@mit.edu'" <granvill@mit.edu>,
        "'jbartels@MIT.EDU'"
	 <jbartels@mit.edu>,
        "'jcentor@mit.edu'" <jcentor@mit.edu>,
        "'momeara@mit.edu'" <momeara@mit.edu>,
        "'rigione@mit.edu'"
	 <rigione@mit.edu>,
        "'schedule@mit.edu'" <schedule@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>,
        "'cgroves@mit.edu'"
	 <cgroves@mit.edu>,
        "'sburke@mit.edu'" <sburke@mit.edu>,
        "'heatherg@mit.edu'" <heatherg@mit.edu>,
        "'prichards@mit.edu'"
	 <prichards@mit.edu>,
        "'cod@mit.edu'" <cod@mit.edu>, "'sjbird@mit.edu'"
	 <sjbird@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        C-Zone
	 <C-Zone@mit.edu>
Date: Fri, 10 May 2002 09:16:16 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	bkaynor@mit.edu; caferrar@mit.edu; Cust-Coach; granvill@mit.edu;
> jbartels@MIT.EDU; jcentor@mit.edu; momeara@mit.edu; rigione@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu; cgroves@mit.edu; sburke@mit.edu;
> heatherg@mit.edu; prichards@mit.edu; cod@mit.edu; sjbird@mit.edu
> Cc: 	shutdown@plant.mit.edu; C-Zone
> Subject: 	Bldg. 12 - Revised, Rescheduled Building Power Shutdown
> 
> 
Dear Everyone:

Because of the Building Power shutdown in Bldg. 12 earlier this week
(Wednesday, 5/8 to verify the breaker feeding the panel outside 12-075 ) it
has been found that two power panels will have to be replaced.  Additional
rooms in Bldg. 12 will be affected by this shutdown.  

The following revised, rescheduled building power shutdown for Bldg. 12 -01
through 08, 056, 064, 073,  084, 087, 090, 091, 092, 093 & 096, 150, 154,
155,164, 169, 170, 170D, 172, 173, 174, 176, 182, 184, 185, 186, 187, 188,
189, 190, 191, 192, 193, 196, 205, 243, show cases (entire East side of
Bldg. 12 - Basement and First Floors) on Saturday, 5/18 is for your
information and comment.   Would you please let me know whether this does or
does not have your approval.

Thank you again for your time.

Andrea Nichols
Repair and Maintenance
8-7872


> Status: Normal
> Building: 12-01 through 08, 056, 064, 073,  084, 087, 090, 091, 092, 093 &
> 096, 150, 154, 155,164, 169, 170, 170D, 172, 173, 174, 176, 182, 184, 185,
> 186, 187, 188, 189, 190, 191, 192, 193, 196, 205, 243, show cases (entire
> East side of B 12 - Basement and First Floors) 
> Date: 5/18/2002
> Day: Saturday
> Time: 7 AM - 12 Noon
> System: Building Power, computers and lighting
> Duration: 5 hours
> Reason: 
> Replace Power Panels.
> 
> Effect: 
> Loss of building power, computers, and lighting in corridors as well as in
> Bldg. 12 - -01 through 08, 056, 064, 073,  084, 087, 090, 091, 092, 093 &
> 096, 150, 154, 155,164, 169, 170, 170D, 172, 173, 174, 176, 182, 184, 185,
> 186, 187, 188, 189, 190, 191, 192, 193, 196, 205, 243, show cases (entire
> East side of Bldg. 12 - Basement and First Floors). 
> 
> 