[59500] in Hotline Meeting
Bldgs. 33/35 - Rescheduled Fire Alarm Shutdown/Live Audible Testi
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 7 11:59:23 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231E3E@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Fire-Prot-Team <rm-fire-prot-team@mit.edu>, B-Zone <B-Zone@mit.edu>,
Cust-Coach <cust-coach@mit.edu>, "'edorsch@mit.edu'" <edorsch@mit.edu>,
"'gallant@mit.edu'" <gallant@mit.edu>,
"'graposa@mit.edu'"
<graposa@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>, "'src@mit.edu'" <src@mit.edu>,
"'gerwent@mit.edu'" <gerwent@mit.edu>,
"'inslee@mit.edu'" <inslee@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'stiffler@mit.edu'" <stiffler@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 7 May 2002 11:59:18 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: RM-Fire-Prot-Team; B-Zone; Cust-Coach; edorsch@mit.edu;
> gallant@mit.edu; graposa@mit.edu; schedule@mit.edu; src@mit.edu;
> gerwent@mit.edu; inslee@mit.edu; shutdowns@mit.edu; stiffler@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. 33/35 - Rescheduled Fire Alarm Shutdown/Live Audible
> Testing
>
>
The following rescheduled fire alarm shutdown/live audible testing in Bldgs.
33/35 now on Saturday, 5/25 is for your information and comment. Would you
please let me know whether this new date does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 33/35
> Date: 5/25/2002
> Day: Saturday
> Time: 7 AM - 4 PM
> System: Fire Alarm/live audible testing of the fire alarm system
> through-out the day.
> Duration: 9 hours
> Reason:
> Make final tie-ins of devices, possible programming, testing - live
> audible testing.
>
> Effect:
> Loss of fire alarm system. If an emergency occurs during the shutdown
> period, please dial either x100 or FIXIT (x3-4948) to report it. Thank
> you.
>
>