[59484] in Hotline Meeting
Bldg. 54 - Rescheduled All Hot and Cold Domestic and Lab Process
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue May 7 08:02:26 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231E2A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'graposa@MIT.EDU'" <graposa@MIT.Edu>,
"'kvkeefe@mit.edu'"
<kvkeefe@MIT.Edu>,
"'politano@mit.edu'" <politano@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.Edu>,
"'w1mx-officers@mit.edu'" <w1mx-officers@MIT.Edu>,
"'wendell@mit.edu'" <wendell@MIT.Edu>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
Warren Scott
<WScott@PLANT.MIT.EDU>,
Jack Allen <jrallen@PLANT.MIT.EDU>,
Dave Hingston <dhingsto@PLANT.MIT.EDU>
Date: Tue, 7 May 2002 08:02:07 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; Cust-Coach; graposa@MIT.EDU; kvkeefe@mit.edu;
> politano@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> w1mx-officers@mit.edu; wendell@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu; Warren Scott; Jack Allen; Dave Hingston
> Subject: Bldg. 54 - Rescheduled All Hot and Cold Domestic and Lab
> Process Water Shutdown Request
>
>
The following rescheduled all hot and cold domestic and lab process water
shutdown request for Bldg. 54 now on Friday, 5/24 is again for your review
and comment. Would you please let me know whether this does or does not
meet with your approval.
Thank you again for your time and I look forward to hearing from you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 54
> Date: 5/24/2002
> Day: Friday
> Time: 7 AM - 4 PM
> System: Domestic and Lab Process Hot and Cold Water
> Duration: 9 hours
> Reason:
> To replace domestic water booster pumping system in basement mechanical
> space.
>
> Effect:
> Loss of hot and cold domestic water (this means that no toilets, bathroom,
> kitchen, lab sink faucets or drining fountains will be operational during
> the shutdown period). Also loss of hot and cold lab process water. This
> means that no lab equipment requiring use of same will be operational
> during the shutdown period.
>
>