Bldgs. 6 and 18 Hot/Cold Lab Process Water Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri May 3 08:07:30 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231DFB@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, "'chemistryhq@mit.edu'" <chemistryhq@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'ghughes@mit.edu'" <ghughes@MIT.Edu>,
        "'glabonte@mit.edu'" <glabonte@MIT.Edu>,
        "'jsheytan@mit.edu'"
	 <jsheytan@MIT.Edu>,
        "'khewitt@mit.edu'" <khewitt@MIT.Edu>,
        "'mhankin@mit.edu'" <mhankin@MIT.Edu>,
        "'rhasselt@MIT.EDU'"
	 <rhasselt@MIT.Edu>,
        "'rrdasari@mit.edu'" <rrdasari@MIT.Edu>,
        "'saraf@mit.edu'" <saraf@MIT.Edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.Edu>,
        "'serotek@mit.edu'" <serotek@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
        "'efrank@mit.edu'"
	 <efrank@MIT.Edu>,
        "'heatherg@mit.edu'" <heatherg@MIT.Edu>,
        "'rjwilk@mit.edu'" <rjwilk@MIT.Edu>, A-Zone <A-Zone@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Fri, 3 May 2002 08:07:23 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	C-Zone; chemistryhq@mit.edu; Cust-Coach; ghughes@mit.edu;
> glabonte@mit.edu; jsheytan@mit.edu; khewitt@mit.edu; mhankin@mit.edu;
> rhasselt@MIT.EDU; rrdasari@mit.edu; saraf@mit.edu; schedule@mit.edu;
> serotek@mit.edu; shutdowns@mit.edu; efrank@mit.edu; heatherg@mit.edu;
> rjwilk@mit.edu; A-Zone
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. 6 and 18 Hot/Cold Lab Process Water Shutdown Request
> 
> 
The following hot/cold lab process water shutdown request for Bldgs. 6 and
18 Labs on Friday, 5/10 is for your information and comment.  Would you
please let me know whether this does or does not have your approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 6 and 18 - Labs
> Date: 5/10/2002
> Day: Friday
> Time: 6 PM - 12 Midnight
> System: Hot/Cold Lab Process Water
> Duration: 6 hours
> Reason: 
> Removing pump discharge line from existing acid waste tank - working
> temporary tank.
> 
> Effect: 
> Loss of hot/cold lab process water in Bldgs. 6 and 18.  This means that no
> equipment requiring use of same will be operational in the labs during the
> shutdown period.
> 
> 