Bldg. 31 - Critical Air Handler 6/Low Pressure Steam/Condensate R

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu May 2 13:18:19 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231DF2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gallant@mit.edu'" <gallant@mit.edu>,
        "'schedule@mit.edu'"
	 <schedule@mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Thu, 2 May 2002 13:18:17 -0400 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	gallant@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 31 - Critical Air Handler 6/Low Pressure
> Steam/Condensate Return Shutdown Request
> 
> 
The following Critical Air Handler 6/Low Pressure Steam/Condensate Return
shutdown request for Bldg. 31 - 222 and 2nd floor radiators on Monday, 5/6
is for your information and comment.  Would you please let me know whether
this does or does not meet with your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Critical
> Building: 31 - 222 and 2nd floor
> Date: 5/6/2002
> Day: Monday
> Time: 7 AM - 9 AM
> System: Air Handler 6/Low Pressure Steam/Condensate Return
> Duration: 2 hours
> Reason: 
> Replace leaking valve in condensate line.
> 
> Effect: 
> Loss of Air Handler 6 (supply heating -- which is probably not on) and low
> pressure steam (radiator heating -- which is also not on) in 31 - 222 and
> rest of the 2nd floor during the 2-hour shutdown period.
> 
> 