RE: Bldg E15 building power shutdown request for 5/3 Updated Info

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed May 1 13:03:41 2002

Message-ID: <568F0AEE7A57D511923900508B556451015624AA@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: barbra@media.mit.edu, E-Zone <E-Zone@MIT.Edu>, fresina@media.mit.edu,
        haller@media.mit.edu, heine@media.mit.edu, kdavis@media.mit.edu,
        tragert@media.mit.edu, schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 1 May 2002 13:03:37 -0400 
MIME-Version: 1.0
Content-Type: text/plain

I am sorry for any confusion but the updated information should be for the
building power shutdown on 5/3.

There is some update information regarding this shutdown you should be aware
of.

There will be a loss of steam and controlled air during this time.  This
includes the server room in 040.  Please let me know if this does or does
not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance

> Status: Normal
> Building: E15
> Date: 5/3/2002
> Day: Friday
> Time: 6am - 10 am
> System: Building Power
> Duration:  4 hours
> Reason: 
> To relocate power panel for renovations in E15 - 015.
> 
> Effect: 
> There will be a loss of building power during this time.
> 
> 