RE: Bldg 54 shutdown request for 5/3/02

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Apr 30 14:25:02 2002

Message-ID: <568F0AEE7A57D511923900508B556451015623B1@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, graposa@MIT.Edu,
        kvkeefe@MIT.Edu, politano@MIT.Edu, schedule@MIT.Edu,
        sdl-adm-lib@MIT.Edu, w1mx-officers@MIT.Edu, wendell@MIT.Edu,
        shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 30 Apr 2002 14:24:42 -0400
MIME-Version: 1.0
Content-Type: text/plain

I am sorry the correct time should read 7am - 4 pm.

Thank you
Dawn Simonelli
Repair and Maintenance




> Status: Normal
> Building: 54
> Date: 5/3/2002
> Day: Friday
> Time: 
> System: All hot & cold domestic and lab processed water
> Duration: 9 hours
> Reason: 
> To replace the domestic water booster pumping system in the basement
> mechanical space.
> 
> Effect: 
> There will be a loss off hot and cold domestic and lab processed water
> during this time.
> 
> 