[59364] in Hotline Meeting
Bldg NW21 shutdown request for 5/1 - 5/3
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Apr 30 09:58:59 2002
Message-ID: <568F0AEE7A57D511923900508B556451013BD0F5@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, fulton@psfc.mit.edu, hrycaj@pfc.mit.edu,
shutdowns@MIT.Edu, schedule@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 30 Apr 2002 09:58:57 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: D-Zone; fulton@psfc.mit.edu; hrycaj@pfc.mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg NW21 shutdown request for 5/1 - 5/3
>
>
The following shutdown request is for building NW21 on the 2nd floor on 5/1
- 5/3. Please let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: NW21 2nd floor offices
> Date: 5/1/2001
> Day: Wednesday
> Time: 7am - 3pm each day
> System: Air conditioning
> Duration: 3 days
> Reason:
> To replace the air conditioner.
>
> Effect:
> There will be a loss of supply air ventilation and supply air cooling
> during this time.
>
>