RE: Bldg 8 - Rescheduled shutdown for building 8 on may 2

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Apr 29 12:13:06 2002

Message-ID: <568F0AEE7A57D511923900508B556451013BD013@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: C-Zone <C-Zone@MIT.Edu>, carolr@MIT.Edu, Cust-Coach
	 <cust-coach@MIT.Edu>,
        ghughes@MIT.Edu, glabonte@MIT.Edu, kmartel@MIT.Edu, lechtman@MIT.Edu,
        schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 29 Apr 2002 12:13:01 -0400
MIME-Version: 1.0
Content-Type: text/plain

The following shutdown request for building 8 is being rescheduled to May 2.
Please let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance



> Status: Normal
> Building: 8 Rooms on a 480 volt power.
> Date: 5/2/02
> Day: Thursday
> Time: 8 am - 3pm
> System: Supply cooling and exhaust.
> Duration: 7 hours
> Reason: 
> Replacing a high voltage switch.
> 
> Effect: 
> There will be no supply air cooling or exhaust general air at this time
> for rooms on 480 volt power.  Which includes 480 volt outlets in room 8 -
> 010, 031 and 014. Also 480 volt loads VFD for PM# 714619 & PM# 714620
> (Mech room 8-116)
> 
> 