[59345] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Bldg 13 - Rescheduled. Shutdown request for compressed lab a

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Apr 29 11:15:45 2002

Message-ID: <568F0AEE7A57D511923900508B556451013BCFFB@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, elk@MIT.Edu,
        generoso@MIT.Edu, schedule@MIT.Edu, src@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 29 Apr 2002 11:15:41 -0400
MIME-Version: 1.0
Content-Type: text/plain

The following shutdown request is being rescheduled to 5/3 from 5/1.  Please
let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance




> Status: Normal
> Building: 13
> Date: 5/3/2002
> Day: Friday
> Time: 7am - 1pm
> System: Compressed Lab Air
> Duration: 6 hours
> Reason: 
> To tie in to power plant compressed air system.
> 
> Effect: 
> There will be no compressed lab air during this time. 
> 
> 