Bldg E19 6th floor shutdown request for 4/30

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Apr 29 10:41:16 2002

Message-ID: <568F0AEE7A57D511923900508B556451013BCFEF@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: bengel@mit.edu, cschultz@mit.edu, dcairns@mit.edu, dlking@mit.edu,
        dreid@mit.edu, dshea@mit.edu, dturn@mit.edu, E-Zone <E-Zone@mit.edu>,
        e19site@mit.edu, elsagt@mit.edu, esico@mit.edu, hallisey@mit.edu,
        honiker@mit.edu, ilf@mit.edu, joconor@mit.edu, kelley@mit.edu,
        kshooter@mit.edu, lambert@mitvma.mit.edu, mbowers@mit.edu,
        Michael Sherman <MSherman@PLANT.MIT.EDU>,
        Mary Tobin
	 <mtobin@PLANT.MIT.EDU>, narbonne@mit.edu, opsnote@mit.edu,
        rberlin@mit.edu, safety@mit.edu, sfalconi@mit.edu,
        Steve Miscowski
	 <SMiscows@PLANT.MIT.EDU>, tdalton@mit.edu,
        tiki@mit.edu, tquinn@mit.edu, wbarrett@mit.edu, wganger@mit.edu,
        schedule@mit.edu, shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 29 Apr 2002 10:41:11 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	bengel@mit.edu; cschultz@mit.edu; dcairns@mit.edu; dlking@mit.edu;
> dreid@mit.edu; dshea@mit.edu; dturn@mit.edu; E-Zone; e19site@mit.edu;
> elsagt@mit.edu; esico@mit.edu; hallisey@mit.edu; honiker@mit.edu;
> ilf@mit.edu; joconor@mit.edu; kelley@mit.edu; kshooter@mit.edu;
> lambert@mitvma.mit.edu; mbowers@mit.edu; Michael Sherman; Mary Tobin;
> narbonne@MIT.EDU; opsnote@mit.edu; rberlin@mit.edu; safety@mit.edu;
> sfalconi@mit.edu; Steve Miscowski; tdalton@mit.edu; tiki@mit.edu;
> tquinn@mit.edu; wbarrett@mit.edu; wganger@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg E19 6th floor shutdown request for 4/30
> 
> 
The following shutdown request for building E19 on 4/30/02.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance


> Status: Normal
> Building: E19 6th floor
> Date: 4/30/2002
> Day: Tuesday
> Time: 7:30 am - 2:30 pm
> System: Fire protection water
> Duration: 7 hours
> Reason: 
> To tie in a new drain to the basement and relocate fire dept 2 1/2"
> valves.
> 
> Effect: 
> There will be a loss of fire protection water during this time.
> 
> 