FW: Bldg. 18 - Rescheduled Fire Protection Water Shutdown for 5/2

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Apr 24 08:24:30 2002

Message-ID: <568F0AEE7A57D511923900508B556451013BCD16@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, chemistryhq@MIT.Edu,
        Cust-Coach
	 <cust-coach@MIT.Edu>, gsj@MIT.Edu, rjwilk@MIT.Edu,
        serotek@MIT.Edu, schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 24 Apr 2002 08:24:25 -0400
MIME-Version: 1.0
Content-Type: text/plain

The following building 18 fire protection water shutdown is being
rescheduled for 5/2/02 from 4/24/02.  Please let me know if this does or
does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: 18 - Basement, Phase II
> Date: 5/2/2002
> Day: Thursday
> Time: 7:30 AM - 2:30 PM 
> System: Fire Protection Water
> Duration: 7 hours each day
> Reason: 
> Tie-in new sprinkler piping in Phase II, additional make safe in Basment.
> 
> Effect: 
> Loss of fire protection water in Bldg. 18 during the 7-hour shutdown
> period.  The Safety Office has been advised of this - that office will
> notify the Fire Department.
> 
> 