Bldg. 68 - Air Handler 1/Supply Fan 1 Rescheduled Filter Change/S

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Apr 17 13:31:54 2002

Message-ID: <568F0AEE7A57D511923900508B55645101231D8C@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'jfucillo@mit.edu'" <jfucillo@MIT.Edu>,
        "'jmganno@mit.edu'"
	 <jmganno@MIT.Edu>,
        "'maureen@mit.edu'" <maureen@MIT.Edu>,
        "'rberlin@mit.edu'" <rberlin@MIT.Edu>,
        "'shyoung@mit.edu'"
	 <shyoung@MIT.Edu>,
        "'wganger@mit.edu'" <wganger@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 17 Apr 2002 13:31:49 -0400
MIME-Version: 1.0
Content-Type: text/plain

> To: 	A-Zone; Cust-Coach; jfucillo@mit.edu; jmganno@mit.edu;
> maureen@mit.edu; rberlin@mit.edu; shyoung@mit.edu; wganger@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 68 - Air Handler 1/Supply Fan 1 Rescheduled Filter
> Change/Shutdown Request
> 
> 
The following rescheduled Air Hander 1/Supply Fan 2 fillter change/shutdown
request for Bldg. 68 - Basement through 6th floors on Thursday, 4/25 is for
your information and comment.  Would you please let me know whether this
does or does not have your approval.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 68 - Basement through 6th floors
> Date: 4/25/2002
> Day: Thursday
> Time: 10 AM - 12 Noon
> System: Air Handler 1/Supply Fan 1 - PM#715496
> Duration: 2 hours
> Reason: 
> Rescheduled Filter changes.
> 
> Effect: 
> Some loss of supply ventilation, supply cooling and supply heating in
> Bldg. 68 - Basement through 6th floors during the 2-hour filter
> change/shutdown request.  Air Handlers 2 and 3 will serve as back-up
> units.
> 
> 