[59052] in Hotline Meeting
Bldg. 13 - Natural Gas, Compressed Lab Air, Hot/Cold Domestic/Lab
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Apr 12 12:24:26 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231D6A@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'elk@mit.edu'" <elk@MIT.Edu>, "'generoso@mit.edu'" <generoso@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>, "'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
"'kurts@mit.edu'"
<kurts@MIT.Edu>,
Paul Stordy <PStordy@PLANT.MIT.EDU>,
"'johnnyd@mit.edu'" <johnnyd@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Billy Homeyer
<whomeyer@PLANT.MIT.EDU>
Date: Fri, 12 Apr 2002 12:24:22 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; elk@mit.edu; generoso@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu; kurts@mit.edu; Paul Stordy;
> johnnyd@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Billy Homeyer
> Subject: Bldg. 13 - Natural Gas, Compressed Lab Air, Hot/Cold
> Domestic/Lab Process Water Shutdown Request
>
>
The following natural gas, compressed lab air, hot/cold domestic/lab process
water shutdown request for Bldg. 13 - 3119 on Tuesday, 4/16 is for your
information. If you have any question about this, please contact Kurt
Samuelson at 8-5962.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 13 - 3119
> Date: 4/16/2002
> Day: Tuesday
> Time: 6 AM - 10 AM
> System: Natural Gas, Comprssed Lab Air, Hot/Cold Domestic/Lab Proces Water
> Duration: 4 hours
> Reason:
> Removing lab services for renovation.
>
> Effect:
> Loss of the above listed services in 13-3119 during the shutdown period.
>
>