[59034] in Hotline Meeting
RE: Bldg. 18 - Approved Tempered Water, DI Water, LP Steam Shutdo
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Apr 11 14:59:59 2002
Message-ID: <568F0AEE7A57D511923900508B556451013BC780@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, chemistryhq@MIT.Edu,
Cust-Coach
<cust-coach@MIT.Edu>, gsj@MIT.Edu, rjwilk@MIT.Edu,
serotek@MIT.Edu
Cc: schedule@MIT.Edu, shutdowns@MIT.Edu, shutdown@PLANT.MIT.EDU
Date: Thu, 11 Apr 2002 14:59:54 -0400
MIME-Version: 1.0
Content-Type: text/plain
I am sorry for any confusion. But this rescheduling should only include the
heating hot water to be rescheduled until April 16.
Thank you
Dawn Simonelli
The following shutdown for building 18 has to be rescheduled. It was
originally scheduled for April 12 but they would like to have this happen on
April 16 form 7am - 9am. Please let me know if this does or does not meet
with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
> Status: Normal
> Building: 18
> Date: 4/12/2002
> Day: Friday
> Time: 5:30 AM - 9:30 AM
> System: Tempered Water, DI Water, LP Steam, Heating Hot Water for reheat
> Duration: 4 hours
> Reason:
> Make piping changes at the bottom of Shaft 2.
>
> Effect:
> Loss of Low Pressure Steam which affects heating hot water for reheat
> (building heat), supply heating, de-ionized water, tempered water (affects
> emergency eyewashes and emergency showers,
>
>