Bldgs. 33 to Bldg. 9 Asbestos Removal Notification
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Apr 10 13:56:23 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231D4F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'edorsch@mit.edu'" <edorsch@MIT.Edu>,
"'gallant@mit.edu'"
<gallant@MIT.Edu>,
"'graposa@MIT.EDU'" <graposa@MIT.Edu>,
"'schedule@mit.edu'" <schedule@MIT.Edu>,
"'sdl-adm-lib@mit.edu'"
<sdl-adm-lib@MIT.Edu>,
"'src@mit.edu'" <src@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
Tim Donaghey
<TDonaghe@PLANT.MIT.EDU>, "'tr6@mit.edu'" <tr6@MIT.Edu>,
"'jdoucett@mit.edu'" <jdoucett@MIT.Edu>,
"'tdoyle@mit.edu'"
<tdoyle@MIT.Edu>,
"'dcosta@mit.edu'" <dcosta@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
Operators
<Operators@PLANT.MIT.EDU>
Date: Wed, 10 Apr 2002 13:56:17 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: B-Zone; Cust-Coach; edorsch@mit.edu; gallant@mit.edu;
> graposa@MIT.EDU; schedule@mit.edu; sdl-adm-lib@mit.edu; src@mit.edu;
> shutdowns@mit.edu; Tim Donaghey; tr6@mit.edu; jdoucett@mit.edu;
> tdoyle@mit.edu; dcosta@mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: Bldgs. 33 to Bldg. 9 Asbestos Removal Notification
>
>
The following asbestos removal notification for Bldg. 33 to Bldg. 9 - 3rd
floor (floor tile - 3 steps) on Friday, 4/19 is for your information. If
you have any questions about this, please contact Tammy Doyle at 3-5166.
Thank you.
Andea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 33 to Bldg. 9 - 3rd floor
> Date: 4/19/2002
> Day: Friday
> Time: 4 PM (4/19) - 4 PM (4/20)
> System: None - asbestos removal notification
> Duration: 24 hours
> Reason:
> Must remove 21 square feet of floor tile in 3 steps.
>
> Effect:
> Area will be cordoned off during the asbestos removal period.
>
>