[58973] in Hotline Meeting
Bldg. 50 - Hot and Cold Domestic Water/Sanitary Waste Drainage Sh
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Apr 8 14:26:46 2002
Message-ID: <568F0AEE7A57D511923900508B55645101231D2F@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'MuddyJoeC@hotmail.com'" <MuddyJoeC@hotmail.com>,
A-Zone
<A-Zone@MIT.Edu>, "'acameron@mit.edu'" <acameron@MIT.Edu>,
"'acomeron@mit.edu'" <acomeron@MIT.Edu>,
Cust-Coach <cust-coach@MIT.Edu>, "'eisen@mit.edu'" <eisen@MIT.Edu>,
"'ekm@mit.edu'" <ekm@MIT.Edu>, "'mwf@mit.edu'" <mwf@MIT.Edu>,
"'pwalsh@mit.edu'" <pwalsh@MIT.Edu>,
"'rberlin@mit.edu'" <rberlin@MIT.Edu>,
"'schedule@mit.edu'"
<schedule@MIT.Edu>,
"'station-manager@wmbr.mit.edu'"
<station-manager@TURNTABLE.mit.edu>,
"'w1mx-officers@mit.edu'"
<w1mx-officers@MIT.Edu>,
"'wganger@mit.edu'" <wganger@MIT.Edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Mon, 8 Apr 2002 14:26:16 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: MuddyJoeC@hotmail.com; A-Zone; acameron@mit.edu; acomeron@mit.edu;
> Cust-Coach; eisen@mit.edu; ekm@mit.edu; mwf@mit.edu; pwalsh@mit.edu;
> rberlin@mit.edu; schedule@mit.edu; station-manager@wmbr.mit.edu;
> w1mx-officers@mit.edu; wganger@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 50 - Hot and Cold Domestic Water/Sanitary Waste
> Drainage Shutdown Request
>
>
The following hot and cold doemstic water/sanitary waste drainage shutdown
request for Bldg. 50 - 1st floor Kitchen on Friday, 4/12 PM is for your
review and comment. Would you please let me know whether this does or does
not meet with your approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 50 - 1st floor Kitchen
> Date: 4/12/2002
> Day: Friday
> Time: 3 PM - 8 PM
> System: Hot and Cold Domestic Water/Sanitary Waste Drainage
> Duration: 5 hours
> Reason:
> Cut into old 4" cast iron pipe - change direction into new grease trap.
>
> Effect:
> Loss of hot and cold domestic water (affects toilets, bathroom, kitchen
> sink faucets, drinking fountains) and sanitary waste drainage in Bldg. 50
> - 1st floor kitchen during the 5-hour shutdown period.
>
>