[58557] in Hotline Meeting
Bldg. E55 - Emergency Building Power Shutdown
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 7 08:01:14 2002
Message-ID: <568F0AEE7A57D511923900508B55645115658D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: RM-Utl <rm-utl@mit.edu>, "'lahappel@mit.edu'" <lahappel@mit.edu>,
"'mlieberm@mit.edu'" <mlieberm@mit.edu>,
"'mwhelan@mit.edu'"
<mwhelan@mit.edu>,
"'management@wmbr.mit.edu'" <management@TURNTABLE.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@mit.edu>,
"'cp-command@mit.edu'"
<cp-command@mit.edu>,
Paul Stordy <PStordy@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>,
"'johnnyd@mit.edu'"
<johnnyd@mit.edu>,
Operators <Operators@PLANT.MIT.EDU>
Date: Thu, 7 Mar 2002 08:01:02 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: RM-Utl; lahappel@mit.edu; mlieberm@mit.edu; mwhelan@mit.edu;
> management@wmbr.mit.edu; shutdowns@mit.edu; cp-command@mit.edu; Paul
> Stordy
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu; johnnyd@mit.edu;
> Operators
> Subject: Bldg. E55 - Emergency Building Power Shutdown
>
>
The following Emergency building power shutdown for Bldg. E55 for today,
Thursday, 3/7 AM is for your information. If you have any question about
this, please contact Paul Stordy at X8-9174.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Emergency
> Building: E55
> Date: 3/7/2002
> Day: Thursday
> Time: 10:30 AM - 12 Noon
> System: Building Power
> Duration: 2 1/2 hours
> Reason:
> Change breaker.
>
> Effect:
> Loss of building power. This means that no lighting in the
> corridors/stairs will be operational during the shutdown period.
>
>