[58408] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 26 - Rescheduled Building Power Shutdown

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 20 13:31:47 2002

Message-ID: <568F0AEE7A57D511923900508B5564511564A4@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'amcgurl@rle.mit.edu'" <amcgurl@rle.mit.edu>, B-Zone <B-Zone@MIT.Edu>,
        Cust-Coach <cust-coach@MIT.Edu>, "'dudley@mit.edu'" <dudley@MIT.Edu>,
        "'kates@mit.edu'" <kates@MIT.Edu>,
        "'khewitt@mit.edu'" <khewitt@MIT.Edu>,
        "'ljtrudel@mit.edu'" <ljtrudel@MIT.Edu>, "'lsc@mit.edu'" <lsc@MIT.Edu>,
        "'mhankin@mit.edu'" <mhankin@MIT.Edu>,
        "'nsteele@mit.edu'"
	 <nsteele@MIT.Edu>,
        "'safety@mit.edu'" <safety@MIT.Edu>,
        "'schedule@mit.edu'" <schedule@MIT.Edu>,
        "'trobins@mit.edu'"
	 <trobins@MIT.Edu>,
        "'wrgibbs@rle.mit.edu'" <wrgibbs@rle.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 20 Feb 2002 13:31:43 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	amcgurl@rle.mit.edu; B-Zone; Cust-Coach; dudley@mit.edu;
> kates@mit.edu; khewitt@mit.edu; ljtrudel@mit.edu; lsc@mit.edu;
> mhankin@mit.edu; nsteele@mit.edu; safety@mit.edu; schedule@mit.edu;
> trobins@mit.edu; wrgibbs@rle.mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - Rescheduled Building Power Shutdown
> 
> 
It has been requested  the building power shutdown for Bldg. 26 - 037, 040,
131, 135, 137, 139, 140, 237, 239, 240, 244, 335, 339, 340, 341, 437, 440,
441, 537, 539, 540 and 541  now take place on  Saturday, March 30.

Would you please let me know whether this new date does or does not meet
with your approval.

Thanks again.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 26 - 037, 040, 131, 135, 137, 139, 140, 237, 239, 240, 244, 335,
> 339, 340, 341, 437, 440, 441, 537, 539, 540 and 541 
> Date: 3/30/2002
> Day: Saturday
> Time: 7 AM - 3 PM
> System: Building Power, comptuers, lighting, supply ventilation, supply
> cooling, exhaust-laboratory, exhaust-general air and exhaust hoods
> Duration: 6 hours
> Reason: 
> Panel change.
> 
> Effect: 
> Loss of power and receptacles - - lighting, fume exhaust fans in 037, same
> in 040 plus make-up air, loss of all of the above in 131, 135, 137, 139,
> 140, 237, 239, 240, 244 Laser Area, 335, 339, 340 (Computer Server for
> Building) and the rest of the rooms mentioned in Building during the
> 6-hour shutdown period.
> 
> 

home help back first fref pref prev next nref lref last post