[58396] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Case 258222: This case has recently been updated

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Feb 20 07:10:14 2002

Message-ID: <568F0AEE7A57D511923900508B556451156493@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'hotline@mit.edu'" <hotline@mit.edu>
Date: Wed, 20 Feb 2002 07:10:12 -0500
MIME-Version: 1.0
Content-Type: text/plain

Will do Lou and thanks.
 Andrea

-----Original Message-----
From: hotline@mit.edu [mailto:hotline@mit.edu]
Sent: Tuesday, February 19, 2002 4:51 PM
To: andrea@PLANT.MIT.EDU
Cc: bmurphy@mit.edu
Subject: Case 258222: This case has recently been updated


Case 258222 has recently been updated and stands as follows.
Please retain the case number in the subject line for future replies
connected with this case.

Most recent entry
=================
(Comment [02/19/2002 16:50:36 by larugsi])

Andrea,
      The only possibility is to go with a few floor fans at this location.
Please advise when this gets confirmed.
                       Thanks Much,
                        --Lou

Case History
============

Email Received [02/12/2002 12:38:49 by daemon]

Date: Tue, 12 Feb 2002 12:38:44 -0500
To: A-Zone <A-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
"'kkgleasn@mit.edu'" <kkgleasn@MIT.Edu>, "'patsys@mit.edu'"
<patsys@MIT.Edu>, "'schedule@mit.edu'" <schedule@MIT.Edu>,
"'swetzel@mit.edu'" <swetzel@MIT.Edu>, "'shutdowns@mit.edu'"
<shutdowns@MIT.Edu>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Subject: Bldg. 66 - Chilled Water Shutdown Request


> To: 	A-Zone; Cust-Coach; kkgleasn@mit.edu; patsys@mit.edu;
> schedule@mit.edu; swetzel@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 66 - Chilled Water Shutdown Request
> 
> 
The following chilled water shutdown request for Bldg. 66 on Friday, 2/22,
Saturday, 2/23 and Sunday, 2/24 is for your information and comment.  Would
you please let me know whether this does or does not meet with your
approval.

Thanks very much.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Normal
> Building: 66
> Date: 2/22/2002
> Day: Friday
> Time: 3 PM (2/22) - 3 PM (2/24)
> System: Chilled Water
> Duration: 48 hours
> Reason: 
> Replacing process chilled water pump
> 
> Effect: 
> Loss of chilled water (air conditioning) and supply cooling via ceiling
> supply fans in all of Bldg. 66 during the 48-hour shutdown period.
> 
> 


Comment [02/12/2002 21:05:17 by larugsi]

Trying to re-schedule.. Andrea looking into.
                  --Lou

Email Received [02/14/2002 19:42:17 by daemon]

Date: Thu, 14 Feb 2002 19:39:40 -0500
To: hotline@MIT.EDU
From: "Louis A. Isgur" <larugsi@MIT.EDU>
Cc: 
Subject: case # 258222



------- Forwarded Message

Return-Path: <andrea@PLANT.MIT.EDU>
Received: from fort-point-station.mit.edu by po11.mit.edu (8.9.2/4.7) id
NAA29491; Wed, 13 Feb 2002 13:09:16 -0500 (EST)
Received: from plantnt.mit.edu (PLANT.MIT.EDU [18.229.1.76])
	by fort-point-station.mit.edu (8.9.2/8.9.2) with ESMTP id NAA28243;
	Wed, 13 Feb 2002 13:09:00 -0500 (EST)
Received: by PLANT.MIT.EDU with Internet Mail Service (5.5.2653.19)
	id <1QJM1VVH>; Wed, 13 Feb 2002 13:08:59 -0500
Message-ID: <568F0AEE7A57D511923900508B556451156451@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'larugsi@mit.edu'" <larugsi@mit.edu>
Cc: "'bmurphy@mit.edu'" <bmurphy@mit.edu>
Subject: Bldg. 66 Chilled Water Shutdown Request
Date: Wed, 13 Feb 2002 13:08:57 -0500
Importance: high
X-Priority: 1
MIME-Version: 1.0
X-Mailer: Internet Mail Service (5.5.2653.19)
Content-Type: text/plain;
	charset="iso-8859-1"

	Lou--

	Here is the response to the question about having this shutdown done
during Spring Break.

	Dear Andrea, we got the pump as soon as we could, it's got to go in
now. As MIT we can't be holding up the completion of this project. We've got
a deadline to meet.  This new process chilled water pump by the way will
solve many problems we've been having in other sections of the building with
one of the causes being Athena room chilled water was taken off of these
existing lines and wiped out any further capacity.  Once we get the new pump
in,  even the computer room will be able to be kept 'cold' on the hottest
summer day.  - Billy

	and then --

	Dear Larry and Winn, I'm getting some feedback from the Athena
people on our 66 chw shutdown a week from Friday. They are concerned about
the cooling being down for 48 hrs., and I'll admit, rightfully so. The rooms
in question are the computer rooms 66-070,080.  What we've done on occasion
in the past is to provide pedestal fans for circulation during such
shutdowns.  I will ask if next week sometime we bring over two pedestal fans
from the stockroom basement, (I've spoken to Tammy), and get them ready to
set up for the weekend shutdown. Doing this will usually allay fear of
severe overheating in computer clusters.  Billy

Lou - based upon this information -- please let me know whether this does or
does not have your approval.

Thanks again.

Andrea Nichols
Repair and Maintenance
8-7872


------- End of Forwarded Message



home help back first fref pref prev next nref lref last post