Bldg. 35 - Emergency Shutdown - Now Includes Bldgs. 33 and 17

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jan 17 14:19:58 2002

Message-ID: <568F0AEE7A57D511923900508B55645115629D@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>,
        "'gerwent@mit.edu'" <gerwent@MIT.Edu>,
        "'inslee@mit.edu'"
	 <inslee@MIT.Edu>,
        "'stiffler@mit.edu'" <stiffler@MIT.Edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.Edu>,
        "'edorsch@mit.edu'"
	 <edorsch@MIT.Edu>,
        "'gallant@mit.edu'" <gallant@MIT.Edu>,
        "'graposa@MIT.EDU'" <graposa@MIT.Edu>,
        "'schedule@mit.edu'"
	 <schedule@MIT.Edu>,
        "'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.Edu>,
        "'src@mit.edu'" <src@MIT.Edu>,
        "'cp-command@mit.edu'"
	 <cp-command@MIT.Edu>,
        "'johnnyd@mit.edu'" <johnnyd@MIT.Edu>,
        Michael Correira <mmcorrei@PLANT.MIT.EDU>,
        "Larry St. John"
	 <lstjohn@PLANT.MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
        "'rm-shutdown@mit.edu'" <rm-shutdown@MIT.Edu>,
        Operators
	 <Operators@PLANT.MIT.EDU>
Date: Thu, 17 Jan 2002 14:19:54 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; gerwent@mit.edu; inslee@mit.edu;
> stiffler@mit.edu; shutdowns@mit.edu; edorsch@mit.edu; gallant@mit.edu;
> graposa@MIT.EDU; schedule@mit.edu; sdl-adm-lib@mit.edu; src@mit.edu;
> cp-command@mit.edu; johnnyd@mit.edu; Michael Correira; Larry St. John
> Cc: 	shutdown@plant.mit.edu; rm-shutdown@mit.edu; Operators
> Subject: 	Bldg. 35 - Emergency Shutdown - Now Includes Bldgs. 33 and
> 17
> 
> 
The following High Pressure Steam Emergency shutdown initially for Bldg. 35
and now includes buildings 33 and 17 for today, Thursday, 1/17 is for your
information.

Thank you.

Andrea Nichols
Repair and Maintenance
8-7872

> Status: Emergency
> Building: 35, 33 and 17
> Date: 1/17/2002
> Day: Thursday
> Time: 2 PM - 7 PM
> System: High Pressure Steam
> Duration: 5 hours
> Reason: 
> Flange leak on high pressure steam on steam station.  Flanges not holding
> - now includes buildings 33 and 17.
> 
> Effect: 
> Loss of high pressure steam. This means there will be no hot domestic
> water (for bathroom and kitchen sink faucets) as well as heating hot water
> (steam heat for buildings involved during the shutdown period.)
> 
> 