[56612] in Hotline Meeting
Bldg. 37 - Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Sep 26 12:25:02 2001
Message-ID: <568F0AEE7A57D511923900508B556451155C33@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Wed, 26 Sep 2001 12:24:59 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 37 - Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. 37 - 2nd and 4th
floor Athena Rooms on Friday, 9/28 is for your information and comment.
Would you please let me know whether this does or does not meet with your
approval.
Thank you.
Andrea Nichols
Repair and Maintenance
8-7872
> Status: Normal
> Building: 37 - 2nd and 4th floor Athena Rooms
> Date: 9/28/2001
> Day: Friday
> Time: 6 AM - 9 AM
> System: Chilled Water
> Duration: 3 hours
> Reason:
> Tie in new variable speed drive.
>
> Effect:
> Loss of chilled water (air conditioning) in 2nd and 4th floor Athena
> Rooms. Air Handler 1 and perimeter areas will not be affected.
>
>