[54061] in Hotline Meeting
Building E23 -Interior Spaces Floors 1 - 4 - Air Handler 9 Emerge
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Mar 1 11:08:58 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451BD1FA2@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'bengel@mit.edu'" <bengel@mit.edu>,
"'dcarlson@mit.edu'"
<dcarlson@mit.edu>,
"'cperry@mit.edu'" <cperry@mit.edu>,
"'baratta@mit.edu'" <baratta@mit.edu>,
"'mmahoney@mit.edu'"
<mmahoney@mit.edu>, E-Zone <E-Zone@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'dwye@med.mit.edu'" <dwye@med.mit.edu>,
"'edwa@med.mit.edu'" <edwa@med.mit.edu>,
"'roge@med.mit.edu'"
<roge@med.mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>,
"'rm-shutdown@mit.edu'" <rm-shutdown@mit.edu>
Date: Thu, 1 Mar 2001 11:08:46 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: bengel@mit.edu; dcarlson@mit.edu; cperry@mit.edu; baratta@mit.edu;
> mmahoney@mit.edu; E-Zone; shutdowns@mit.edu; dwye@med.mit.edu;
> edwa@med.mit.edu; roge@med.mit.edu
> Cc: shutdown@plant.mit.edu; rm-shutdown@mit.edu
> Subject: Building E23 -Interior Spaces Floors 1 - 4 - Air Handler 9
> Emergency Shutdown - 3/1
>
>
The following emergency shutdown for Bldg. E23 (Air Handler 9) for today,
Thursday, 3/1 is for your information. If you have any question about this,
please contact Craig Venezia at 3-0635.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: E23 - floors 1 - 4 interior spaces
> Date: 3/1/2001
> Day: Thursday
> Time: 10:45 AM - unknown
> System: Air Handler 9 (supply ventilation, supply cooling, supply heating)
> Duration: unknown
> Reason:
> Need to replace FCS controls.
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating in the
> interior spaces - floors 1 thru 4 during the shutdown period.
>
>