Shutdown request for building 13 on 2/26 - 3/2

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Feb 13 12:16:31 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451EE8CC4@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, elk@MIT.Edu,
        mcoleman@MIT.Edu, schedule@MIT.Edu, src@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 13 Feb 2001 12:16:16 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; elk@mit.edu; mcoleman@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 13 on 2/26 - 3/2
> 
> 
The following shutdown request is for building 13 on 2/26 - 3/2.  Please let
me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: 13 Center and east exhaust fan risers
> Date: 2/26/01
> Day: Monday
> Time: 6am  2/26 - 2 pm 3/2
> System: Exhuast fans 10 and 14 (no hoods are involved)
> Duration: 5 days
> Reason: 
> To install new motors.
> 
> Effect: 
> There will be a loss of general air exhaust.
> 
> 