[53814] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Shutdown request for building 36 on 2/15 & 16

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Feb 12 14:56:39 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451EE8B37@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: amcgurl@rle.mit.edu, B-Zone <B-Zone@MIT.Edu>,
        Cust-Coach
	 <cust-coach@MIT.Edu>, schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 12 Feb 2001 14:56:27 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	amcgurl@rle.mit.edu; B-Zone; Cust-Coach; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 36 on 2/15 & 16
> 
> 
The following shutdown request is for building 36 on 2/15 & 2/16.  Please
let me know if this does  or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: 36
> Date: 2/15/01
> Day: Thursday
> Time: 7:30 am - 3:30 pm
> System: Fire protection water
> Duration: 8 hours
> Reason: 
> Demolition
> 
> Effect: 
> There will be a loss of fire protection water during this time.
> 
> 

home help back first fref pref prev next nref lref last post