Shutdown request for building 13 on 2/20 - 2/23

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Feb 12 09:19:42 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451EE87FB@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, elk@MIT.Edu,
        mcoleman@MIT.Edu, schedule@MIT.Edu, src@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Mon, 12 Feb 2001 09:19:35 -0500
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; elk@mit.edu; mcoleman@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 13 on 2/20 - 2/23
> 
> 
The following shutdown request is for building 13 rooms 4011, 4023, 4027,
4047, 4055, 4059, 4071, and 4079 on 2/20 - 2/23.  Please let me know if this
does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: 13 rooms 4011, 4023, 4027, 4047, 4055, 4059, 4071, and 4079
> Date: 2/20/01
> Day: Tuesday
> Time: 6 am on 2/20 until 2 pm 2/23
> System: Chilled water
> Duration: 4 days
> Reason: 
> To relocate valves in corridors to accomadate new duct work.
> 
> Effect: 
> There will be a loss of chilled water in rooms listed above during this
> time.
> 
> 