Shutdown request for building 13 on February 14, 15, & 16

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Feb 9 14:02:21 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451EE8764@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: B-Zone <B-Zone@MIT.Edu>, Cust-Coach <cust-coach@MIT.Edu>, elk@MIT.Edu,
        mcoleman@MIT.Edu, schedule@MIT.Edu, src@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 9 Feb 2001 14:02:07 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	B-Zone; Cust-Coach; elk@mit.edu; mcoleman@mit.edu; schedule@mit.edu;
> src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 13 on February 14, 15, & 16
> 
> 
The following shutdown request is for building 13 on February 14, 15 and 16
.  Please let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599	

> Status: Normal
> Building: 13 rooms 4011, 4024, 4028, 4040, 4048, 4056, 4060, 4072, and
> 4080
> Date: 2/14/01
> Day: Wednesday
> Time: 6am 2/14 - 2 pm  2/16
> System: Fan coil chilled water system
> Duration: 3 days
> Reason: 
> To relocate valves in corridors to accomodate new duct work.
> 
> Effect: 
> There will be a loss of chilled water during this time.
> 
> 