FW: Shutdown request for building W13 on 2/13
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Feb 5 08:37:00 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451E216B5@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: shutdowns@mit.edu
Date: Mon, 5 Feb 2001 08:36:45 -0500
MIME-Version: 1.0
Content-Type: text/plain;
charset="iso-8859-1"
-----Original Message-----
From: Dawn Simonelli [mailto:dsimone@PLANT.MIT.EDU]
Sent: Monday, February 05, 2001 8:32 AM
To: D-Zone; kcn@MIT.EDU; mwhelan@MIT.EDU
Cc: shutdown@plant.mit.edu
Subject: Shutdown request for buiding W13 on 2/13
> To: D-Zone; kcn@mit.edu; mwhelan@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for buiding W13 on 2/13
>
>
The following shutdown request is for building W13 on 2/13. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: W13
> Date: 2/13/01
> Day: Tuesday
> Time: 7:30 am - 4:00 pm
> System: Emergency power
> Duration: 8 1/2 hours
> Reason:
> To relocate ATS from south wall to north wall per plans.
>
> Effect:
> There will be a loss of emergency power during this time.
>
>