[53593] in Hotline Meeting
Shutdown request for building 14E 109 on 2/1
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jan 25 12:39:28 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451E21041@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, jsbanks@MIT.Edu, schedule@MIT.Edu,
sdl-adm-lib@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 25 Jan 2001 12:39:18 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; jsbanks@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 14E 109 on 2/1
>
>
The following shutdown request is or building 14E room 109 on 2/1. Please
let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 14E - 109
> Date: 2/1/01
> Day: Thursday
> Time: 7:30 am - 2:30 pm
> System: AH3
> Duration: 7 hours
> Reason:
> Replace chilled water supply valve.
>
>
> Effect:
> There will be a loss of chilled water during this time.
>
>