[53591] in Hotline Meeting
Shutdown request for builiding 18 on 2/8
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jan 25 11:29:46 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451E2102F@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, akelsey@MIT.Edu,
Cust-Coach
<cust-coach@MIT.Edu>, mbj@MIT.Edu, rjwilk@MIT.Edu,
schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 25 Jan 2001 11:29:39 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for builiding 18 on 2/8
>
>
The following shutdown request is for building 18 on 2/8. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 18
> Date: 2/8/01
> Day: Thursday
> Time: 6 pm - 7 am
> System: Plumbing Systems (during power shutdown)
> Duration: 13 hours
> Reason:
> Add valves to pipes feeding the Phase 2 shaft t avoid additional shutdown
> later.
>
> Effect:
> There will be a loss of hot and cold domestic water, hot lab processed
> water, compressed lab air, and lab vacuum air.
>
>