[53585] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Emergency shutdown for E23 dental department & 4th floor surgical

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jan 25 06:47:53 2001

Message-Id: <82F0D564C5ADD31180EF00508B556451E20FBD@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.EDU>, bengel@MIT.EDU, dwye@med.mit.edu,
        edwa@med.mit.edu, roge@med.mit.edu, shutdowns@MIT.EDU,
        schedule@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 25 Jan 2001 06:47:33 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	E-Zone; bengel@mit.edu; dwye@med.mit.edu; edwa@med.mit.edu;
> roge@med.mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Emergency shutdown for E23 dental department & 4th floor
> surgical area 
> 
> 
The following emergency shutdown for E23 dental department and 4th floor
surgical area from 1-25 through 1-28 is for your information.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Emergency
> Building: E23 Dental department & 4th floor surgical area
> Date: 1/25/01
> Day: Thursday
> Time:             
> System: Dental vacuum system
> Duration: 4 days
> Reason: 
> Major repairs to vacuum pump and piping in mechanical room.
> 
> Effect: 
> There will be a loss of lab vacuum air during this time.
> 
> 

home help back first fref pref prev next nref lref last post