[53561] in Hotline Meeting
Shutdown request for buildings E17, E18 and E19 on 1/26
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Jan 23 08:33:10 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451E20DF7@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: bengel@MIT.EDU, E-Zone <E-Zone@MIT.EDU>, jmganno@MIT.EDU, lombardo@MIT.EDU,
shyoung@MIT.EDU, wardd@MIT.EDU, bengel@MIT.EDU, dudley@MIT.EDU,
E-Zone <E-Zone@MIT.EDU>, jmganno@MIT.EDU, lombardo@MIT.EDU,
lstcroix@MIT.EDU, nsteele@MIT.EDU, safety@MIT.EDU, shyoung@MIT.EDU,
cschultz@MIT.EDU, dcairns@MIT.EDU, dlking@MIT.EDU, dshea@MIT.EDU,
dturn@MIT.EDU, E-Zone <E-Zone@MIT.EDU>, e19site@MIT.EDU,
elsagt@MIT.EDU, esico@MIT.EDU, hallisey@MIT.EDU, honiker@MIT.EDU,
joconor@MIT.EDU, kelley@MIT.EDU, kshooter@MIT.EDU,
lambert@mitvma.mit.edu, lkn@MIT.EDU, mbowers@MIT.EDU,
Mary Tobin <mtobin@PLANT.MIT.EDU>, opsnote@MIT.EDU, rberlin@MIT.EDU,
rrhonda@MIT.EDU, safety@MIT.EDU, sfalconi@MIT.EDU,
Steve Miscowski <SMiscows@PLANT.MIT.EDU>, tdalton@MIT.EDU,
tmeehan@MIT.EDU, wbarrett@MIT.EDU, shutdowns@MIT.EDU, schedule@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 23 Jan 2001 08:33:00 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: bengel@mit.edu; E-Zone; jmganno@mit.edu; lombardo@mit.edu;
> shyoung@mit.edu; wardd@mit.edu; bengel@mit.edu; dudley@mit.edu; E-Zone;
> jmganno@mit.edu; lombardo@mit.edu; lstcroix@mit.edu; nsteele@mit.edu;
> safety@mit.edu; shyoung@mit.edu; cschultz@mit.edu; dcairns@mit.edu;
> dlking@mit.edu; dshea@mit.edu; dturn@mit.edu; E-Zone; e19site@mit.edu;
> elsagt@mit.edu; esico@mit.edu; hallisey@mit.edu; honiker@mit.edu;
> joconor@mit.edu; kelley@mit.edu; kshooter@mit.edu; lambert@mitvma.mit.edu;
> lkn@mit.edu; mbowers@mit.edu; Mary Tobin; opsnote@mit.edu;
> rberlin@mit.edu; rrhonda@mit.edu; safety@mit.edu; sfalconi@mit.edu; Steve
> Miscowski; tdalton@mit.edu; tmeehan@mit.edu; wbarrett@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for buildings E17, E18 and E19 on 1/26
>
>
The following shutdown request is for buildings E17, E18, and E19 on 1/26.
Please let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: E17, E18, and E19
> Date: 1/26/01
> Day: Friday
> Time: 7:30 am - 11:30 am
> System: Fire alarms
> Duration: 4 hours
> Reason:
> Test flow and tamper switches on shaft riser.
>
> Effect:
> The fire alarms will be down during this time.
>
>