[53533] in Hotline Meeting
Shutdown request for building 18 on 2/8
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Mon Jan 22 09:51:28 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451E20CAE@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, akelsey@MIT.EDU,
Cust-Coach
<cust-coach@MIT.EDU>, mbj@MIT.EDU, rjwilk@MIT.EDU,
schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Mon, 22 Jan 2001 09:51:19 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 18 on 2/8
>
>
The following shutdown request is for building 18 on 2/8. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 18
> Date: 2/8/01
> Day: Thursday
> Time: 5 pm - 7am
> System: All 480 volt equipment and 277 volt lighting system for building
> Duration: 12 hours (overnight)
> Reason:
> Install new primary switch #2 install a temporary transformer and panels
> for 480/277 systems.
>
> Effect:
> There will be a loss of building power (480 volt), lighting (277 volt),
> chilled water, heating hot water, supply air ventilation, supply air
> cooling, supply air heating, exhaust lab air, high, medium and low
> pressure steam, condensate return steam and fire protection water.
>
>