Shutdown request for building E18 2nd floor on 1/24

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 19 12:07:41 2001

Message-Id: <82F0D564C5ADD31180EF00508B556451E20BAD@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: bengel@MIT.EDU, dudley@MIT.EDU, E-Zone <E-Zone@MIT.EDU>, jmganno@MIT.EDU,
        lombardo@MIT.EDU, lstcroix@MIT.EDU, nsteele@MIT.EDU, safety@MIT.EDU,
        shyoung@MIT.EDU, schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 19 Jan 2001 12:07:25 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	bengel@mit.edu; dudley@mit.edu; E-Zone; jmganno@mit.edu;
> lombardo@mit.edu; lstcroix@mit.edu; nsteele@mit.edu; safety@mit.edu;
> shyoung@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building E18 2nd floor on 1/24
> 
> 
The following shutdown request is for building E18 on 1/24.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: E18 second floor
> Date: 1/24/01
> Day: Wednesday
> Time: 5 am- 11:30 am
> System: Hot water reheat all of 2nd floor
> Duration: 6 hours
> Reason: 
> Demo and rework in rooms 209, 208, 206, 211 etc.
> 
> Effect: 
> There will be a loss of supply air heating, and heating hot water.
> 
> 