[53507] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Shutdown request for building E34 on 1/24

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 19 11:21:26 2001

Message-Id: <82F0D564C5ADD31180EF00508B556451E20B97@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: E-Zone <E-Zone@MIT.EDU>, politano@MIT.EDU, wendell@MIT.EDU,
        schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 19 Jan 2001 11:21:18 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	E-Zone; politano@mit.edu; wendell@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building E34 on 1/24
> 
> 
The following shutdown request for building E34 first floor on 1/24/01.
Please let me know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: E34 first floor
> Date: 1/24/01
> Day: Wednesday
> Time: 7 am - 11am
> System: Heating hot water too all fan coil units on 1st floor.
> Duration: 4 hours
> Reason: 
> Remove supply and return lines to fan coil unit.  Cut in new lines for fan
> coil in room 146.
> 
> Effect: 
> There will be no heat on the first floor.
> 
> 

home help back first fref pref prev next nref lref last post