Shutdown request for building 18 on 1.24

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 19 09:40:22 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451E20B6A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, akelsey@MIT.Edu,
        Cust-Coach
	 <cust-coach@MIT.Edu>, mbj@MIT.Edu, rjwilk@MIT.Edu,
        schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 19 Jan 2001 09:40:14 -0500
MIME-Version: 1.0
Content-Type: text/plain

To: 	A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; rjwilk@mit.edu;
schedule@mit.edu; shutdowns@mit.edu
Cc: 	shutdown@plant.mit.edu
Subject: 	Shutdown request for building 18 on 1.24


The following shutdown request is for building 18 on 1/24/01.  Please let me
know if this does or does not meet with your approval.

Status: Normal
Building: 18
Date: 1/24/01
Day: Wednesday
Time: 7 am - 3:30 pm
System: Fire protection water
Duration: 8 1/2 hours
Reason: 
Connect north stairwell standpipe to mainm cap phase 1 shaft riser connect
flow switches to alarm.

Effect: 
There will be a loss of fire protection water and alarms.