Shutdown request for building W8 on 1/24/01

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Jan 17 13:57:50 2001

Message-Id: <82F0D564C5ADD31180EF00508B556451D2C49B@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.EDU>, djmartin@MIT.EDU, gham@MIT.EDU, slett@MIT.EDU,
        schedule@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Wed, 17 Jan 2001 13:57:20 -0500
Mime-Version: 1.0
Content-Type: text/plain

> To: 	D-Zone; djmartin@mit.edu; gham@mit.edu; slett@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building W8 on 1/24/01
> 
> 
The following shutdown request is for building W8 on 1/24/01.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: W8 Men's shower
> Date: 1/24/01
> Day: Wednesday
> Time: 7 am - 3 pm
> System: Hot and cold domestic water
> Duration: 8 hours
> Reason: 
> Repair shower valves.
> 
> Effect: 
> There will be a loss of hot and cold domestic water.
> 
> 