[53419] in Hotline Meeting
Shutdown request for 26 on 1/18 - 19
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 12 14:51:41 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451D2C29A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: almcgurl@mit.edu, andreab@mit.edu, B-Zone <B-Zone@mit.edu>,
Cust-Coach
<cust-coach@mit.edu>, dudley@mit.edu, gfp170@rle.mit.edu,
kates@mit.edu, ljtrudel@mit.edu, lsc@mit.edu, mhankin@mit.edu,
nsteele@mit.edu, radams@mit.edu, safety@mit.edu, schedule@mit.edu,
shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 12 Jan 2001 14:51:28 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: almcgurl@mit.edu; andreab@mit.edu; B-Zone; Cust-Coach;
> dudley@mit.edu; gfp170@rle.mit.edu; kates@mit.edu; ljtrudel@mit.edu;
> lsc@mit.edu; mhankin@mit.edu; nsteele@mit.edu; radams@mit.edu;
> safety@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for 26 on 1/18 - 19
>
>
The following shutdown request is for building 26 on 1/ 18 and 19. Please
let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 26 rooms 031 - 033
> Date: 1/18/01
> Day: Thursday
> Time: &:30 am - 3:30 pm
> System: Exhaust fume hood.`
> Duration: 8 hours each day
> Reason:
> Install new duct work.
>
> Effect:
> There will be a loss of exhaust lab air.
>
>