Shutdown request for building 56 rooms 254, 367B, 454, 670, 738B,
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Jan 10 14:26:10 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451D2C06A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.Edu>, jmganno@MIT.Edu, shyoung@MIT.Edu,
schedule@MIT.Edu, shutdowns@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Wed, 10 Jan 2001 14:25:56 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: A-Zone; jmganno@mit.edu; shyoung@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 56 rooms 254, 367B, 454, 670,
> 738B, 754, and 046A on 1/22
>
>
The following shutdown request is for building 56 on 1/22. Please let me
know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 56 rooms 254, 367B, 454, 670, 738B, 754, and 046A
> Date: 1/22/01
> Day: Monday
> Time: 11am - 3 pm
> System: Fan Exhaust PM# 718063
> Duration: 4 Hours
> Reason:
> Preventive maintenance
>
>
> Effect:
> There will be a loss of open slot exhaust during this time.
>
>