[53368] in Hotline Meeting
Shutdown request for building 18 on 1/11/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Wed Jan 10 11:32:25 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451D2BFF8@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: A-Zone <A-Zone@MIT.EDU>, akelsey@MIT.EDU,
Cust-Coach
<cust-coach@MIT.EDU>, mbj@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU, rjwilk@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Wed, 10 Jan 2001 11:32:15 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: A-Zone; akelsey@mit.edu; Cust-Coach; mbj@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; rjwilk@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for building 18 on 1/11/01
>
>
The following shutdown request is for building 18 on 1/11/01. Please let
me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 18
> Date: 1/11/01
> Day: Thursday
> Time: 3 pm - 3 pm
> System:
> Duration: 1 day
> Reason:
> 1 - To drain TFO's so the pipes don't freeze during the power outage. 2
> Weld new connection into the yard.
>
>
> Effect:
> There will be a loss of fire protection water during this time.
>
>