Shutdown request for building 13 on 1/10/01

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Jan 9 09:09:07 2001

Message-ID: <82F0D564C5ADD31180EF00508B556451D2BE8A@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andreab@mit.edu, B-Zone <B-Zone@mit.edu>,
        Cust-Coach
	 <cust-coach@mit.edu>, mcoleman@mit.edu, rhasselt@mit.edu,
        schedule@mit.edu, src@mit.edu, shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Tue, 9 Jan 2001 09:09:01 -0500 
MIME-Version: 1.0
Content-Type: text/plain

> To: 	andreab@mit.edu; B-Zone; Cust-Coach; mcoleman@mit.edu;
> rhasselt@mit.edu; schedule@mit.edu; src@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Shutdown request for building 13 on 1/10/01
> 
> 
The following shutdown request is for building 13 on 1/10/01.  Please let me
know if this does or does not meet with your approval.

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599

> Status: Normal
> Building: 13
> Date: 1/10/01
> Day: Wednesday
> Time: 6 am - 2 pm
> System: AH2
> Duration: 8 hours
> Reason: 
> To tie in center supply on the third floor.
> 
> 
> Effect: 
> There will be a loss of supply heating during this time.
> 
> 