[53324] in Hotline Meeting
Shutdown request for buildings 7 & 5 on 1/15/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Jan 5 07:26:45 2001
Message-Id: <82F0D564C5ADD31180EF00508B556451D2BC6C@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: blose@MIT.EDU, depopolo@MIT.EDU, jbnorman@MIT.EDU, mdhinkle@MIT.EDU,
slester@MIT.EDU, hover@MIT.EDU, jmcollin@MIT.EDU, peggyb@MIT.EDU,
sclinton@MIT.EDU, skendall@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 5 Jan 2001 07:26:38 -0500
Mime-Version: 1.0
Content-Type: text/plain
> To: blose@mit.edu; depopolo@mit.edu; jbnorman@mit.edu; mdhinkle@mit.edu;
> slester@mit.edu; hover@mit.edu; jmcollin@mit.edu; peggyb@mit.edu;
> sclinton@mit.edu; skendall@mit.edu; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for buildings 7 & 5 on 1/15/01
>
>
The following shutdown request is for builidings 7 & 5 on 1/15/01. Please
let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: 7 & 5
> Date: 1/15/01
> Day: Monday
> Time: 7 am - 3pm
> System: Control air and air pressure to operate 7 lobby doors
> Duration: 8 hours
> Reason:
> To tie in at main power plant compressed air.
>
> Effect:
> There will be a loss of supply air cooling and compressed control air.
>
>