[53317] in Hotline Meeting
Shutdown request for buiding E18 on 1/10/01
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Thu Jan 4 09:52:09 2001
Message-ID: <82F0D564C5ADD31180EF00508B556451D2BBD7@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: Joe Vella <jpvella@PLANT.MIT.EDU>, schedule@mit.edu, shutdowns@mit.edu
Cc: shutdown@PLANT.MIT.EDU
Date: Thu, 4 Jan 2001 09:50:36 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: Joe Vella; schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Shutdown request for buiding E18 on 1/10/01
>
>
The following shutdown request is for E18's carpenter's shop on 1/10/01.
Please let me know if this does or does not meet with your approval.
Thank you
Dawn Simonelli
Repair and Maintenance
2-1599
> Status: Normal
> Building: E18 Carpenter's Shop
> Date: 1/10/01
> Day: Wednesday
> Time: 7:30 am - 9 :30 am
> System: Compressed Air
> Duration: 2 hours
> Reason:
> Replace the pressure switch
>
> Effect:
> There will be a loss of compressed air.
>
>