Emergency shutdown for NW16
daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Fri Dec 29 07:42:21 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451D2B983@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: D-Zone <D-Zone@MIT.Edu>, fulton@psfc.mit.edu, hrycaj@pfc.mit.edu,
shutdowns@MIT.Edu, schedule@MIT.Edu
Cc: shutdown@PLANT.MIT.EDU
Date: Fri, 29 Dec 2000 07:42:15 -0500
MIME-Version: 1.0
Content-Type: text/plain
> To: D-Zone; fulton@psfc.mit.edu; hrycaj@pfc.mit.edu; shutdowns@mit.edu;
> schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Emergency shutdown for NW16
>
>
There is an emergency shutdown for building NW16 on 12/29.
Thank you
DawN Simonelli
> Status: Emergency
> Building: NW16
> Date: 12/29/00
> Day: Friday
> Time: Until about 8am
> System: Boiler
> Duration: 1 hour
> Reason:
> Boiler is having a minor problems.
>
> Effect:
> The heat will be off until 8am but it may take a while to heat up the
> building again.
>
>