Bldg. E40 - 7/22 - Electrical (120/208V) Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 19 13:21:44 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451105096@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'cfoglia@mit.edu'" <cfoglia@MIT.EDU>,
        "'danibon@mit.edu'"
	 <danibon@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>,
        "'gwj@mit.edu'"
	 <gwj@MIT.EDU>,
        "'michaela@mit.edu'" <michaela@MIT.EDU>,
        "'pmosley@mit.edu'" <pmosley@MIT.EDU>,
        "'pvargas@mit.edu'"
	 <pvargas@MIT.EDU>,
        "'schung@mit.edu'" <schung@MIT.EDU>,
        "'jweiss@mit.edu'" <jweiss@MIT.EDU>,
        "'shutdowns@mit.edu'"
	 <shutdowns@MIT.EDU>,
        "'lfm@mit.edu'" <lfm@MIT.EDU>, "'jfob@mit.edu'"
	 <jfob@MIT.EDU>,
        "'rklester@mit.edu'" <rklester@MIT.EDU>,
        "'jdb@mit.edu'"
	 <jdb@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Wed, 19 Jul 2000 13:20:51 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	cfoglia@mit.edu; danibon@mit.edu; E-Zone; gwj@mit.edu;
> michaela@mit.edu; pmosley@mit.edu; pvargas@mit.edu; schung@mit.edu;
> jweiss@mit.edu; shutdowns@mit.edu; lfm@mit.edu; jfob@mit.edu;
> rklester@mit.edu; jdb@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. E40 - 7/22 - Electrical (120/208V) Shutdown Request
> 
> 
The following electrical (120/208V) shutdown request for Bldg. E40 on
Saturday, July 22 is for your information and comment.  Would you please let
me know whether this does or does not meet with your approval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: E40
> Date: 7/22/00
> Day: Saturday
> Time: 7:30 AM - 11:30 AM
> System: Electrical (120/208V) - Riser bus duct 2nd floor electrical room
> Duration: 4 hours
> Reason: 
> Adding bus duct switch for new 120 Volt panel.
> 
> Effect: 
> Loss of power:  access controls (supply ventilation, supply cooling,
> supply heating), building power, freight elevator, computers and lighting
> during the 4-hour shutdown period.
> 
> 