E25 on the first floor on 7/20

daemon@ATHENA.MIT.EDU (Dawn Simonelli)
Tue Jul 18 09:23:52 2000

Message-Id: <82F0D564C5ADD31180EF00508B556451754318@PLANT.MIT.EDU>
From: Dawn Simonelli <dsimone@PLANT.MIT.EDU>
To: andrea@wccf.mit.edu, andreab@MIT.EDU, bengel@MIT.EDU, bmalone@MIT.EDU,
        cpoon@MIT.EDU, E-Zone <E-Zone@MIT.EDU>, elworthi@MIT.EDU,
        hegarty@MIT.EDU, jkay@mitppl.mit.edu, jmganno@MIT.EDU, jrauch@MIT.EDU,
        lippertm@MIT.EDU, rfink@MIT.EDU, roge@med.mit.edu, schedule@MIT.EDU,
        sdl-adm-lib@MIT.EDU, sdowney@MIT.EDU, shyoung@MIT.EDU,
        shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 18 Jul 2000 09:23:06 -0400
Mime-Version: 1.0
Content-Type: text/plain

> To: 	andrea@wccf.mit.edu; andreab@mit.edu; bengel@mit.edu;
> bmalone@mit.edu; cpoon@mit.edu; E-Zone; elworthi@mit.edu; hegarty@mit.edu;
> jkay@mitppl.mit.edu; jmganno@mit.edu; jrauch@mit.edu; lippertm@mit.edu;
> rfink@mit.edu; roge@med.mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> sdowney@mit.edu; shyoung@mit.edu; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	E25 on the first floor on 7/20
> 
> 
The following shutdown request for building E25 first floor on July 20th  is
for supply air.   Please let me know if this does or does not meet your
approval.  

Thank you
Dawn Simonelli
Repair and Maintenance
2-1599  

> Status: Normal
> Building: E25 first floor
> Date: 7/20/00
> Day: Thursday
> Time: 7:30am  - 3:00pm 
> System: Supply air - Building , ah7
> Duration: 7 1/2 hours
> Reason: 
> The repair of the supply air ducts - new duct installation.
> 
> Effect: 
> no supply ventilation and no supply cooling.
> 
> 