[51300] in Hotline Meeting
Bldg. E52 - Air Handlers 1, 2, 3, 4, & 5 - 7/11 PM Shutdown Reque
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 6 08:04:38 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104FEC@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'andreab@mit.edu'" <andreab@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'gwj@mit.edu'" <gwj@MIT.EDU>, "'jbkalb@mit.edu'"
<jbkalb@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>,
"'lmorales@mit.edu'" <lmorales@MIT.EDU>,
"'lreinher@mit.edu'"
<lreinher@MIT.EDU>,
"'maureen@mit.edu'" <maureen@MIT.EDU>,
"'michaela@mit.edu'" <michaela@MIT.EDU>,
"'mscoppa@mit.edu'"
<mscoppa@MIT.EDU>, "'mwf@mit.edu'" <mwf@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Thu, 6 Jul 2000 08:04:18 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: andreab@mit.edu; shutdowns@mit.edu; gwj@mit.edu; jbkalb@mit.edu;
> lhill@mit.edu; lmorales@mit.edu; lreinher@mit.edu; maureen@mit.edu;
> michaela@mit.edu; mscoppa@mit.edu; mwf@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E52 - Air Handlers 1, 2, 3, 4, & 5 - 7/11 PM Shutdown
> Request
>
>
The following Air handlers shutdown request for Bldg. E52 on Tuesday, July
11 PM is for your review and comment. Would you please let me know whether
this meets with your approval or does not. The Faculty Club has approved
this shutdown for that time.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E52
> Date: 7/11/00
> Day: Tuesday
> Time: 5 PM - 11 PM
> System: Air Handlers 1, 2, 3, 4 and 5
> Duration: 6 hours
> Reason:
> To repair OA dampers, RA dampers, Ex Dampers, reheat control valve and
> chilled water supply valve.
>
> Effect:
> Loss of supply ventilation, supply cooling (with the exception of computer
> rooms that have fan coil units) during the 6-hour shutdown period.
>
>