[51234] in Hotline Meeting
Bldg. E53 - 6/27- Chilled Water Shutdown Request
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 23 09:17:35 2000
Message-Id: <82F0D564C5ADD31180EF00508B556451104F3B@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'crf@mit.edu'" <crf@MIT.EDU>, "'e-zone@mit.edu'" <e-zone@MIT.EDU>,
"'gwj@mit.edu'" <gwj@MIT.EDU>, "'janets@mit.edu'" <janets@MIT.EDU>,
"'lhill@mit.edu'" <lhill@MIT.EDU>,
"'michaela@mit.edu'"
<michaela@MIT.EDU>,
"'schedule@mit.edu'" <schedule@MIT.EDU>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.EDU>,
"'shutdown@mit.edu'"
<shutdown@MIT.EDU>
Cc: "'shutdown@plant.mit.edu'" <shutdown@plant.mit.edu>
Date: Fri, 23 Jun 2000 09:14:08 -0400
Mime-Version: 1.0
Content-Type: text/plain
> To: crf@mit.edu; e-zone@mit.edu; gwj@mit.edu; janets@mit.edu;
> lhill@mit.edu; michaela@mit.edu; schedule@mit.edu; sdl-adm-lib@mit.edu;
> shutdown@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E53 - 6/27- Chilled Water Shutdown Request
>
>
The following chilled water shutdown request for Bldg. E53 on Tuesday, June
27 is for your information and comment. Would you please let me know
whether this does or does not have your approval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E53
> Date: 6/27/00
> Day: Tuesday
> Time: 8 AM - 11 AM
> System: Chilled Water cooling
> Duration: 4 hours
> Reason:
> Change two - 4" pneumatic valves
>
> Effect:
> Loss of chilled water (air conditioning) in Bldg. E53 during the shutdown
> period.
>
>