Bldg. 66 - Subbasement and floors 1 thru 5 - 7/22 PM Shutdown Re
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 20 11:38:44 2000
Message-ID: <82F0D564C5ADD31180EF00508B556451104EF0@PLANT.MIT.EDU>
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'patsys@mit.edu'" <patsys@mit.edu>,
"'shutdowns@mit.edu'"
<shutdowns@mit.edu>,
"'schedule@mit.edu'" <schedule@mit.edu>
Cc: "'shutdown@plant.mit.edu'" <shutdown@PLANT.MIT.EDU>
Date: Tue, 20 Jun 2000 11:36:13 -0400
MIME-Version: 1.0
Content-Type: text/plain
> To: patsys@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 66 - Subbasement and floors 1 thru 5 - 7/22 PM
> Shutdown Request
>
>
The following preventive maintenance shutdown request for Bldg. 66 -
Subbasement and floors 1 thru 5 north on Friday, July 23 is for your
information and comment. Would you please let me know whether this does or
does not meet with your appproval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 66 - Subbasement and floors 1 thru
> Date: 7/22/00
> Day: Friday
> Time: 7 AM - 3 PM
> System: Air Handler 1/Return Fan 3
> Duration: 2 hours between 7 & 3 PM
> Reason:
> Preventive maintenance work on AH1 - RF3 which will shutdown supply
> ventilation to Bldg. 66.
>
> Effect:
> Loss of supply ventilation (general air) to Bldg. 66 - Floors 1through 5
> North during the 8-hour shutdown period. A listing of the rooms that would
> be affected are: 125 through 185A, 221A thru 217; 225 thru 285A, 317 thru
> 369, 408 thru 471and 508 thru 521.
>
>